Maplewood Park: $2.5 Million Authorized, and What the City's Records Show

The city's response to MNN's records request includes three cost estimates, a $1.4 million construction contract, and a $332,500 engineering proposal. Here is the record, the arithmetic, and what is missing.

What is the city up to at Maplewood Park? MNN filed a public records request on September 25, 2026 to find out, and the city's planning office answered on October 5, four days ahead of its own deadline.1 The request asked for the cost estimates, the project management and vendor contracts, and the City Council papers that authorize funding for installing artificial turf at the park.

This article is a statement of the record. It sets out what the documents say, adds up the numbers they contain, and lists what they do not contain. It does not claim that any money has been misspent. The records the city sent are commitments and estimates, not payments.

A screenshot of MNN's request 2026-0448 in the City of Malden's FOIAdirect portal, showing a sent date of 09/25/2026, a response due date of 10/09/2026, a response sent date of 10/05/2026, and the text of the request.
MNN's request 2026-0448 as shown in the city's FOIAdirect portal.

The request, in full:

What the Council authorized

On December 10, 2024, the City Council adopted Paper 426 of 2024 by an 11 to 0 vote, appropriating $2,500,000 from available general fund free cash for Maplewood Park Turf Rehabilitation. The order was sponsored by Carey McDonald, and Mayor Gary Christenson approved it on December 17.2

The mayor's November 26, 2024 memo to the Council described the request as a surface replacement, saying the field "no longer passes the various applicable tests." It called $2.5 million a budget figure to be refined by a design, and said the work was a rip-and-replace, not a complete makeover of the park. It also said the city was using free cash to avoid borrowing for smaller capital needs.3

Editorial note: In a September 12, 2022 story MNN reported a City representative was about the field condition of Maplewood Park at that time: "They smiled, and stated that it was in fine condition." The MNN article attached the City’s own report issued on 6/14/19, which stated at that time:

“The field as a whole is observed to be in poor condition due to excessive fiber wear through out entire field. …Field is at end of life and replacement in near future is recommended.”

Three estimates

The response includes three cost documents, all prepared by or for the project's designer. Each is an opinion of probable cost. The two Activitas documents carry a standard caution that actual bids may differ, and the December 2025 summary is marked as a draft for discussion.456

Cost estimates in the records
DocumentBase scopeAlternatesNotes
Activitas, Dec. 6, 2022 (preliminary programming)$2,227,305.51$500,640.00 (LED relamp)Total $2,727,945.51. The December 2025 summary rounds this to $2,728,000.
Activitas, Dec. 12, 2025 (preliminary design)$1,387,149.58Seven alternates, about $539,700 in totalConstruction only, with 6% general conditions, 12% overhead and profit, and 20% contingency. No soft costs.
Draft summary, Dec. 19, 2025$1,664,600$647,600Adds a 20% soft-cost allowance (design, permitting, bidding, construction administration). Grand total $2,312,200, against a $2,500,000 authorization.

Between the two Activitas documents the scope shrank. The field area fell from 118,336 square feet to 104,323, down 11.8 percent. Replacement of fencing and netting, priced in the 2022 base, moved to optional alternates in 2025. The lighting item changed from a $298,000 LED relamp alternate to a $25,000 relamping allowance in the base. The turf price rose from $4.75 to $5.25 per square foot. The 2022 estimate also included permanent soccer, field hockey and lacrosse lines, and the 2025 estimate prices only baseball lines.

IMEG's February 2026 proposal says the work would revisit the 2022 scope and cost in light of the city's fiscal position and its interest in paring back the project to reduce cost.7 The $2,500,000 authorization is about $228,000 below the 2022 total and $187,800 above the December 2025 draft total with every alternate.

Contracts and commitments

Construction. On May 18, 2026 the city and R.A.D. Corp. d/b/a R.A.D. Sports signed the Maplewood Park Improvements agreement. It covers the base bid plus Bid Alternates 1 and 2, with liquidated damages of $1,500 per day. The performance bond and the labor and materials bond are each for $1,395,279.00, the bid amount shown on the change orders.8 Addendum No. 1, dated April 13, 2026, describes Bid Alternate 2 as work along the field's perimeter fence, including warning-track material and the fence's bottom rail.9 The records do not say what Bid Alternate 1 covers.

Change orders. Change Order 01 adds $27,460: $22,460 to replace 12 broken lenses and repair seven lighting outages, and $5,000 for imported stone under the walkway, where the existing asphalt was 1 to 2 inches thicker than expected. It was signed August 25 and 26, 2026.10 Change Order 02 adds $7,200 for clearing trees and brush from a drainage swale behind the first-base dugout. The engineer signed it September 3, the contractor September 25, and the owner, through OSPCD, September 28.11 Together they raise the contract by $34,660, or 2.5 percent, to $1,429,939.00.

Engineering. IMEG Consultants Corp.'s February 9, 2026 work order proposal sets a total estimated fee of $332,500, which it says will not be exceeded without the city's prior approval. The copy produced, titled Executed, is addressed to OSPCD Director Alex Pratt and includes an acceptance block for the city, though the signature and date are hard to read in the scan.7

IMEG estimated fee, February 9, 2026
PhaseAmount
Programming services$25,000.00
Design and permitting services$65,000.00
Bidding and contract award assistance$12,500.00
Construction administration support (24 weeks)$55,000.00
Construction observation (20 weeks, 240 hours)$45,000.00
Sports field consultant (allowance, Activitas as subcontractor)$125,000.00
Reimbursable expenses (allowance)$5,000.00
Total estimated fee$332,500.00

The fee is $55,100 above the $277,400 soft-cost allowance the draft December summary set for the base scope, and below the $385,300 allowance for the base scope plus all alternates.

Adding it up

Authorization against documented commitments
ItemAmountSource
Authorization (Paper 426-24)$2,500,000.00Council order, Dec. 2024
R.A.D. Sports contract as adjusted by Change Orders 01 and 02$1,429,939.00Contract and change orders
IMEG estimated fee$332,500.00IMEG proposal, Feb. 2026
Documented commitments$1,762,439.00MNN's sum
Authorization not accounted for by the documents$737,561.00 (29.5%)MNN's difference

The $737,561 is not a finding of anything. It is the part of the authorization that the produced records do not tie to a contract, an estimate or a payment. It could reflect costs that were never part of the request, such as testing, environmental work or contingency, or it could be unspent. MNN's request did not ask for invoices or payment records, so the response does not show how much has actually been paid.

What the records do not show

Timeline

Dates in the records
DateEvent
Dec. 6, 2022Activitas preliminary programming estimate: $2,727,945.51 including the LED relamp alternate.
Nov. 26, 2024Mayor's free cash memo asks for $2.5 million for Maplewood Park.
Dec. 10, 2024City Council adopts Paper 426-24, 11 to 0.
Dec. 17, 2024Mayor approves Paper 426-24.
Dec. 12 and 19, 2025Activitas preliminary design estimate and draft summary: $1,664,600 base, $2,312,200 with all alternates.
Jan. 1, 2026Term of the Hayner Swanson on-call agreement ends.
Feb. 9, 2026IMEG work order proposal, $332,500 estimated fee.
Apr. 13, 2026Addendum No. 1 issued to plan holders.
May 18, 2026Contract signed with R.A.D. Sports; bonds of $1,395,279.00.
Aug. 25 to 26, 2026Change Order 01, $27,460.
Sept. 3 to 28, 2026Change Order 02, $7,200, signed in three stages.
Sept. 25, 2026MNN files request 2026-0448.
Oct. 5, 2026City responds.

Questions for the city

If you have information about this project, or see something in the records we have missed, write to MaldenNewsNetwork@gmail.com. The documents are linked below so you can read them yourself.

Records received in response to request 2026-0448
Notes
  1. Public records request 2026-0448 to the Office of Strategic Planning and Community Development (OSPCD), submitted by Malden News Network through the city's FOIAdirect portal September 25, 2026; response due October 9, 2026; response sent October 5, 2026. ←
  2. City of Malden, attested copy of Paper 426 Series of 2024, adopted by the City Council December 10, 2024 (11 yea, 0 nay), approved by the Mayor December 17, 2024. ←
  3. Mayor Gary Christenson, memorandum to the City Council, Free Cash Appropriation, November 26, 2024. ←
  4. Activitas, Itemized Opinion of Probable Construction Costs, Maplewood Park Field Renovation, Project No. 22051.00, Preliminary Programming, December 6, 2022. ←
  5. Activitas, Itemized Opinion of Probable Costs, Maplewood Park Field Renovation, Project No. 25044, Preliminary Design, December 12, 2025. ←
  6. Summary, Preliminary Opinion of Probable Project Cost, Maplewood Park Field Renovation, marked Draft for Discussion, December 19, 2025. ←
  7. IMEG Consultants Corp., Professional Services Work Order Proposal, Maplewood Park Improvements, February 9, 2026, with acceptance by the City and 2026 hourly rate schedule. ←
  8. City of Malden and R.A.D. Corp. d/b/a R.A.D. Sports, Agreement (Section 3), Maplewood Park Improvements, dated May 18, 2026, with performance and labor-and-materials bonds ($1,395,279.00 each), power of attorney and certificate of insurance. The posted copy covers one private home address on page 4. ←
  9. IMEG Consultants Corp., Addendum No. 1, Maplewood Park Improvements, April 13, 2026. ←
  10. Change Order No. 01, Maplewood Park Improvements, signed August 25 and 26, 2026. ←
  11. Change Order No. 02, Maplewood Park Improvements, signed September 3, 25 and 28, 2026. ←
  12. City-Vendor Agreement between the City of Malden and Hayner Swanson, Inc. for on-call civil engineering services, January 1, 2023. ←
  13. Agreement for Professional Services between the Malden Redevelopment Authority and Hayner/Swanson, Inc., July 22, 2015, with Amendments No. 1 through No. 3. ←
  14. Confirmatory Deed, Trafton Park, executed June 9, 2021, citing City Council Paper 288 of 2021. ←
  15. Parking License Agreement between Malden Catholic High School, Inc. and Malway Realty Associates Limited Partnership, effective June 5, 2024. ←
A disclosure: This article is built from the 14 documents the City of Malden's Office of Strategic Planning and Community Development sent MNN on October 5, 2026 in response to public records request 2026-0448, all linked below. Several are scanned images, so amounts and dates transcribed from them should be checked against the linked originals. One document is posted in a copy with a private individual's home address covered. Comparisons and arithmetic are MNN's own and are shown in the text. Claude (Anthropic) assisted with organizing and editing the text under the editor's direction; the editor is responsible for the facts and quotations.
Primary AI assistance: Claude (Anthropic)
Corrections: This piece reflects our understanding of the matter as of publication and is based on public documents. We make reasonable efforts to ensure substantial accuracy. If you believe we've gotten a significant fact wrong, please email us so we can look into it.
Email: MaldenNewsNetwork@gmail.com