The Malden City Council voted 10-1 on Tuesday, October 20, to move $2,230,219.50 in funding authorized for the Roosevelt Park Revitalization Project over to the Malden River Works. Each of the two orders, 393-26 and 394-26, had its own motion and roll call, and each drew the same lone "no" vote: At-Large Councillor Karen Colón Hayes.1
Order 393-26 repurposes $1,292,045 that remained from the cash appropriation in Paper 139 of 2023. Order 394-26 transfers $938,174.50 from the borrowing authorized in Paper 140 of 2023, funds the order describes as no longer needed to finish the project they were obtained for. Both orders were sponsored by Finance Committee Chair Carey McDonald.2 They were previously headed for the October 6 meeting, then moved to the October 20 meeting when the agenda was revised.
On October 22, we emailed Mayor Christenson and two members of his staff five questions for this story, including which version of the 2018 park plan the city preferred, how the Mayor's sign-off requirement for Community Preservation applications has been applied to community proposals, and what the administration plans for the rest of the park. We asked for a reply by 5:00 p.m. on October 27. As of publication we have received neither answers nor an acknowledgment. We will update this article if the Mayor's Office responds.
Why the Council Said It Had to Act Now
The argument from the Council floor was about the clock. According to Councillor McDonald, the prior Roosevelt Park project was canceled and a new, narrower project covering only the soil remediation took its place, so the older authorizations had nothing left to fund. OSPCD Director Alex Pratt and the City Treasurer added the federal angle: the city borrowed this money, it is earning interest on it, and the IRS expects borrowed funds to be spent promptly rather than parked. The Treasurer told the Council that a paper like this cannot be amended from the floor, and that money cannot be assigned to a project that does not exist.1
What Is Left for the Park
The cleanup now underway is paid for separately, by a Section 108 loan that carried over from the original project, McDonald told colleagues. Ward 5 Councillor Ari Taylor said that work will restore the outdoor classroom and, for the first time in about seven years, reopen the whole park. Beyond that, McDonald said, there is no plan, no assigned staff, no timeline and no cost estimate for anything more. Taylor said she intends to rebuild community involvement and bring a plan forward, but that building one will take more than a few months and that the money needs to be used now.1 The scaled-down remediation covers roughly 16,000 square feet of fenced area, according to the filing we reported on earlier.3
The $200,000 That Never Got a Vote
Colón Hayes proposed setting aside $200,000 of the transfer to pay for a Roosevelt Park planning process. Councillor O'Malley said he would have seconded it. She withdrew the idea after the Treasurer's answer, then voted no on both papers. McDonald added a second obstacle: the Council can approve or reduce spending the Mayor proposes, they said, but cannot redirect it to a purpose of its own. McDonald promised that any leftover River Works money would be the first place the Council looks for Roosevelt Park planning costs, and asked for a final accounting once bids are settled. Colón Hayes also disclosed that she sits on the River Works steering committee and the board of the Mystic River Watershed Association.1
The Clock, in the Council's Own Words
"...we have probably delayed it longer than we should." - Councillor Carey McDonald, October 20, 2026, on the bonding authorization, https://www.youtube.com/live/tDkD2U9DWp8?si=kD3HHbdo0Kf7_Aq2&t=5189
That admission is the center of this story. The Roosevelt Park Improvement Project was canceled on April 29, 2024, about two and a half years before this vote.4 McDonald said the bond authorization had been held longer than it should have been, and that sitting on borrowed money can affect the city's credit rating. Colón Hayes called leaving the money unused a bad financial decision. Their remarks put the delay on the record.1
The Warning on the Record
One piece of that history sits in the Council's own files. On April 25, 2023, the Community Preservation Committee wrote to Councillor McDonald, then as now chair of the Finance Committee. The CPC recommended reallocating a $1.45 million Community Preservation Act bond, approved in 2019, to remove contaminated soil across the whole park to a depth of 36 inches, with any remainder going to site preparation. The letter said the CPC had asked the MRA/OSPCD and the Council for a scope change in 2021 and was told that changes to the approved scope could not be made unless city officials directed them. It also warned that the bond order capped interest at 4.25 percent and would become null above that rate, noted the project had stalled for four years, and offered to rescind the bond so the CPC could close out roughly $200,000 it had held for the project since 2019.5 The public records we have do not establish whether that bond is the same borrowing as Paper 140 of 2023, one of the two sources of this transfer (see "What We Still Don't Know," below).
| Date | What happened | Source |
|---|---|---|
| 2010 | City says it began looking at upgrades to the site | 2018 CPC pre-application |
| 2014 | City returns a PARC grant it could not match | 2018 CPC pre-application |
| Apr 17, 2018 | Concept plan prepared for the Malden Redevelopment Authority | 2018 CPC pre-application |
| May 1, 2018 | FY19 pre-application deadline; Mayor Christenson and Councillor Murphy named as applicants | 2018 CPC pre-application |
| 2019 | A $1.45M CPA bond is approved | CPC letter |
| Dec 2019 | Lead is reported at the park and a section is fenced off | Earlier Broadside reporting |
| Jul 23, 2020 | CPC receives an application from affiliates of the Friends of Roosevelt Park | CPC records |
| Mar and Jul 2021 | CPC asks to add soil mitigation to the project scope | CPC letter |
| Apr 25, 2023 | CPC asks the Finance Committee to redirect the bond to 36-inch mitigation or rescind it | CPC letter |
| 2023 | Council adopts Papers 139 and 140 as additional project funding | Council agenda; Oct 20 remarks |
| Apr 29, 2024 | The Mayor cancels the Roosevelt Park Improvement Project | Earlier Broadside reporting |
| May 30, 2024 | A neighbor and abutter submits a community application (FY25-0023) | CPC records |
| Jul 14, 2026 | Remediation plan filed for a roughly 16,000 sq ft fenced area | MassDEP filings |
| Sep 22, 2026 | The Mayor asks to reappropriate about $2.2M to the River Works | Earlier Broadside reporting |
| Oct 20, 2026 | Council adopts Orders 393-26 and 394-26, 10-1 | Council meeting |
| Oct 21, 2026 | CPC tells a community inquirer a pre-application must be signed by the Mayor | CPC response |
Who Could Have Acted?
The record does not show one body that dropped the ball, and we are not claiming it does. The CPC letter says the MRA/OSPCD told it that a scope change needed direction from city officials. The 2023 letter was addressed to the Finance Committee chair and copied to five other councillors: Condon, O'Malley, Colón Hayes, Simonelli and Linehan. All six were on the roll call vote: five voted yes and Colón Hayes voted no.51 By the CPC's account, each body held part of the decision and pointed to another for the rest.
Set the CPC's request beside what has actually happened. In 2023 the CPC asked for soil mitigation across the entire site to a landscaping depth of 36 inches. The remediation plan filed in July 2026 covers a much smaller fenced area. Our earlier reporting on the MassDEP records describes the same gap.3 The rest of the park has no plan and, in McDonald's words, no project for the Council to fund.
How It Began: A Mayor's Pre-Application
To understand how the park got here, it helps to go back to the start. The earliest applications to the Community Preservation Committee are public records, and one of the first and largest was the Roosevelt Park Improvement Project. Its FY19 pre-application, due May 1, 2018, lists Mayor Gary Christenson and Councillor Barbara Murphy as the applicants, with Malden Redevelopment Authority Executive Director Deborah Burke as the contact person. It proposes a multi-sport field on the 3.76-acre site at Salem and Branch Streets beside the Salemwood School, with an "outdoor classroom" element.6
The form priced two versions: about $2.435 million for a synthetic turf field with associated infrastructure, and about $2.848 million for a sand-based natural grass field. It said the city had been looking to upgrade the site since 2010, and that it had returned a state PARC grant in 2014 because it could not raise the additional money the project needed. A concept plan dated April 17, 2018 and prepared for the Malden Redevelopment Authority by the engineering firm Hayner/Swanson, Inc. came attached. Eight years after that filing, and sixteen after the date the form gives for the city's first efforts, the park has a partial cleanup and no plan for the rest.6
A Different Path for Community Proposals
Others tried to bring their own ideas to the CPC. Affiliates of the Friends of Roosevelt Park submitted an application that the CPC received on July 23, 2020. A neighbor and abutter of the park submitted another, FY25 application CPC-0023, "Renovation of Roosevelt Park Phase 1," on May 30, 2024.7
The paperwork describes the route such proposals must take. The 2018 form says the City of Malden must be a co-applicant on every project on city property. And in a response to a community inquiry dated October 21, 2026, about an off-cycle application for Roosevelt Park soil management and remediation, the CPC said it would need a pre-application with an agreed-upon project description "signed by the Mayor," because the land is city-owned.68 On the CPC's account, that makes the Mayor's signature a gate for proposals on city land. The Mayor's own 2018 pre-application arrived with his name on it and a concept plan prepared for a public body, the Malden Redevelopment Authority. A community proposal he did not endorse could not advance without his signature. The documents show the requirement as the CPC now describes it. They do not show whether it governed the 2020 and 2024 applications, how often it has been used, or whether it was ever used to turn a proposal away. We asked the Mayor on October 22 how the requirement has been applied; he did not respond.
Residents Recall a Dispute Over Turf
We interviewed three residents, each more than once, whom we consider credible. We are withholding their names. Each fears retaliation for speaking in favor of more progress at Roosevelt Park. Two recalled the Mayor's position on the park's design, described below. The third described an early Community Preservation Committee meeting; we have not included that account because we did not put it to the committee. What follows are recollections. We have no recording or document of the remarks they describe, and we have not independently corroborated them.9
One recalled the Mayor saying, in meetings with community groups, that he would not improve the park unless it included an artificial turf field. A second recalled him treating neighbors' environmental costs from turf as "opportunity costs" he was willing to take. We put these recollections to the Mayor on October 22; he did not respond.9
As these residents describe it, the dispute came down to a simple contrast: the Mayor wanted artificial turf, while the Friends of Roosevelt Park, neighbors and, in their account, a consensus of Salemwood School interests wanted natural grass. The paper record is less tidy. The 2018 pre-application priced both a turf and a natural grass field and does not say on its face which the city preferred.6
The Ward Councillor Names the Animosity
Councillor Ari Taylor, who represents Ward 5, where the park sits, acknowledged the strain on October 20. She said bringing the community back together has been difficult because there was "a lot of animosity around this." More than one group cares about Roosevelt Park, she said, and there are many voices, many of whom felt shut out of the last conversation. For the past couple of years, she said, she has been working to bring everyone back to the table.1 In this passage she did not say what the dispute was about or whom the shutting-out was attributed to.
What We Still Don't Know
The 2023 CPC letter and the 2023 Council papers may or may not describe the same money, and the public records we have do not say. Several answers would settle the question and show what happens next:
- Was the $1.45 million CPA bond in the 2023 letter the same borrowing as Paper 140 of 2023, and what became of the roughly $200,000 CPC earmark?
- What response, if any, did the Finance Committee give the CPC after April 25, 2023?
- How much of the $2,230,219.50 will the River Works actually spend, and specifically what will it be spent on? When will the final accounting McDonald requested be public?
- When, and through what process, will a plan for the rest of Roosevelt Park begin, and what funding source/s will it use?
- How many community-submitted Roosevelt Park proposals reached the CPC, and did any receive a recorded decision? How often has the Mayor's signature requirement decided the outcome?
-
View PDF →2023-04-25 CPC Letter to the Finance Committee (Roosevelt Park)
-
View PDF →2018 CPC FY19 Pre-Application, Roosevelt Park Improvement Project (with April 17, 2018 concept plan)
-
View PDF →2024-05-30 CPC FY25-0023, Renovation of Roosevelt Park Phase 1 (community application)
-
View source →Roosevelt Park: what the City's soil records show (earlier Broadside reporting)
-
View source →Roosevelt Park Money Moves (earlier Broadside reporting)